At the morning production meeting, Loom 12 shows 970 metres against a 1,500-metre daily plan. Before sending maintenance to the loom, the supervisor checks which shifts submitted readings. If the night shift is missing, part of the apparent shortage is still unconfirmed. A useful loom production report puts that difference on the same screen as the metre totals.
Start with one record per loom, date and shift
Agree on when the production date changes for an overnight shift. Record the loom, job card or fabric style, applicable beam reference, target metres, actual metres, stoppage minutes and primary reason. Split production between job cards when a loom changes style during a shift. Keep the shift target aligned with planned running time and the style being woven.
Use three distinct outcomes: submitted output, confirmed zero output and entry pending. Confirmed zero can be correct for a loom waiting for a beam or down for repairs. A pending entry should appear in the supervisor's follow-up list until the shift reading is reconciled.
Read the shortfall in two parts
Suppose Loom 12 has a target of 500 metres in each of three shifts. Shift A records 480 metres, shift B records 490 metres and shift C is pending. The report should show 970 metres confirmed against a 1,000-metre target for the two reported shifts. The confirmed shortfall is 30 metres. The remaining 500 metres of planned production belongs to a shift that still needs verification.
If the night shift later confirms 450 metres, the loom finishes the day at 1,420 metres against 1,500 metres. The 80-metre shortfall is then ready for review. The supervisor can check whether the supporting records show beam change, warp or weft breaks, a mechanical stop or another reason. Keep time and metre figures separate so the manager can see the recorded evidence before assigning a cause.
Close the report in the morning meeting
- The shift operator records the metre reading and stop reason at handover. Use a consistent rule for counter resets and roll changes.
- The shift supervisor resolves missing or duplicate readings and confirms zero-output shifts with a reason.
- The production head reviews confirmed shortfalls by loom and job card, then assigns maintenance, materials or planning follow-up as appropriate.
- The planning team uses confirmed output when reviewing open job cards and expected fabric availability. If dispatch relies on inspected fabric, reconcile the woven metres with the next stage before promising a quantity.
Pilot the workflow on one loom group
During a Decent ERP implementation, the Decent team and the mill's production head can map loom codes, job cards, shift boundaries and approval responsibilities. Ask the operators to enter one full day's production and the supervisor to reconcile it with the shift sheets. Test one genuine zero-output shift, one late entry and one style change. Confirm that the owner can tell which figures are verified and who must resolve each exception before expanding to other loom groups.
Explore Decent's Textile Manufacturing ERP or book a demo with a sample shift sheet and one job card from your weaving unit.