A Bhiwandi weaving planner has a 1,000-metre fabric order. The yarn ledger shows 180 kg in stock, yet the job may still be short. Beam planning starts with the yarn the design needs, then checks how much of the matching count and shade lot is actually free to issue.
Calculate the warp requirement from the approved design
Set the total warp ends, yarn count, planned fabric length and approved allowances in the design or job card. Use the yarn count system that your mill actually buys in. The example below uses tex, where 1 tex is 1 gram per 1,000 metres. If the buyer measures finished metres, first convert that target to the corresponding planned loom length using your mill’s approved conversion. The 1,000 metres here is already the planned loom length.
In this example, the design has 3,000 total warp ends at 40 tex. The mill applies a 5% warp take-up allowance and adds 30 metres per end for setup and beam-end allowance. Planned warp length per end is 1,000 × 1.05 + 30 = 1,080 metres. Total warp yarn is 3,000 × 1,080 × 40 ÷ 1,000,000 = 129.6 kg. Confirm that the loom can take the beam and check the separate weft requirement before scheduling production.
Check usable stock by count and lot
The store has 125 kg from the approved lot and 55 kg from another shade lot. Of the approved 125 kg, 25 kg is reserved for a different job. That leaves 100 kg available against 129.6 kg required. The approved lot is 29.6 kg short, even though total stock is 180 kg. Keep the job on hold until the short quantity is supplied or an alternate lot is explicitly approved. If the order permits a shorter run, revise the job and recalculate fixed allowances before issuing yarn.
Reconcile the yarn after warping
Once the shortage is resolved, the storekeeper issues the yarn against the job card. Suppose 132 kg is issued, 128 kg goes on the beam, 3 kg returns to usable stock and 1 kg is recorded as waste. The issue balances: 132 = 128 + 3 + 1 kg. The supervisor then compares the 128 kg on the beam with the planned 129.6 kg and verifies the measured beam length before releasing it to the loom.
Test one live workflow during ERP implementation
The Decent implementation team and your planner can map design inputs, yarn lot rules and job-card approvals using one fabric style. Your storekeeper checks reservations and records issues and returns. Your warping supervisor validates actual length and weight. Test one normal beam and one lot shortage, then check whether the planner can see why a job is held and who needs to act.